Show on map
Benson City of — Power plant · Oil · City of Benson - (MN)
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Benson City of

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2002
Net generation, 2025
114 MWh
Grid
115 kV, 14 kV to City of Benson - (MN) (MISO)
Location
Swift County, Minnesota
Operated by
City of Benson - (MN)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2025
Fuel burned MMBtu by year, 2002 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Technology
Oil source: “Petroleum Liquids”
Age
24 years since 2002
Unused energy
79 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
9,684 Btu/kWh 2025
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 20251,104
Capacity factor, 20250.001
Heat rate (Btu/kWh), 20259,684.2
Net generation (MWh), 2025114
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
2.2 MW
Generators retired
2
Capacity still in service
9 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
5Petroleum Liquids0.9 MWRetiredMay 2013
6Petroleum Liquids1.3 MWRetiredMay 2013

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
115 kV, 14 kV
Transmission or distribution system owner
City of Benson - (MN)
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
MRO
Transmission lines within 15 mi (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 5, 6 scheduled to retire, 2.2 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 27, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source