Cashton Greens Wind Farm
Power plant · Wind
Key facts
Power plant · Windran 22% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2012
- Net generation, 2025
- 9,815 MWh
- Grid
- 4 kV to Village of Cashton - (WI) (MISO)
- Location
- Monroe County, Wisconsin
- Operated by
- Cashton Greens Wind Farm LLC
Output
Details
Who’s behind it
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Technology
- Wind source: “Onshore Wind Turbine”
- Age
- 14 years since 2012
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Gem |
|
| Grid |
|
| Fuel burned (MMBtu), 2025 | 33,489 |
| Capacity factor, 2025 | 0.224 |
| Net generation (MWh), 2025 | 9,815 |
| Balancing authority code | MISO |
Wind turbines
- Turbines
- 2
- Turbine capacity (MW)
- 5
- Turbine models
- 2 Clipper C96
- Hub height (m)
- 100
- Rotor diameter (m)
- 96
- Year online
- 2012
Source U.S. Wind Turbine Database
Source
- U.S. Wind Turbine DatabaseMap services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb
Ownership
3 companies3| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| CROPP Cooperative | Owner | 50.0% | Dec 31, 2025 | EIA-860 |
| GL Envision LLC | Owner | 50.0% | Dec 31, 2025 | EIA-860 |
| Cashton Greens Wind Farm LLC | Operator | EIA-860M |
Timeline
- In service · EIA-860M
Sources
6 sourcesSources EIA-860M · GEM · U.S. Wind Turbine Database · EIA · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
- U.S. Wind Turbine DatabaseMap services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
- EIA-860M Preliminary Monthly Electric Generator Inventory