Show on map
Elroy - Hosensack Kv Sub 500 kV — Transmission lineWest Point (PA) — Under construction · Gas, reciprocating engine · PA · 2.5 MW · 4.4 mi awayTIERPOINT TWO, LLC - TEKPARK FACILITY — Built · Large load · PA · 10.0 mi awayFLEXENTIAL/ UPPER PROVIDENCE TWP — Built · Large load · PA · 11.3 mi awayVALLEY FORGE DIGITAL UTILITY FACILITY / LOWER PROVIDENCE — Built · Large load · PA · 11.5 mi awayCSL BEHRING DATA CTR/KING OF PRUSSIA — Built · Large load · PA · 13.1 mi awayINNOVATION 2201 LLC / UPPER MERION TWP — Built · Large load · PA · 13.3 mi away
  • Combustion
  • Loads
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Elroy - Hosensack Kv Sub 500 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
500 kV
States crossed
US-PA
Owner (as stated)
PPL Electric Utilities

Details

Who’s behind it

Owner
PPL Electric Utilities

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Mapped route length (miles)
18
Substations at the ends (as the source names them)
Elroy to Hosensack Kv Sub
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itppl electric utilities
HIFLD line ID101384
Voltage class500 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
West Point (PA) Under construction Gas, reciprocating engine 4.4 mi 2.5
TIERPOINT TWO, LLC - TEKPARK FACILITY Built Large load 10.0 mi
FLEXENTIAL/ UPPER PROVIDENCE TWP Built Large load 11.3 mi
VALLEY FORGE DIGITAL UTILITY FACILITY / LOWER PROVIDENCE Built Large load 11.5 mi
CSL BEHRING DATA CTR/KING OF PRUSSIA Built Large load 13.1 mi
INNOVATION 2201 LLC / UPPER MERION TWP Built Large load 13.3 mi

Sources EIA-860M · EPA ICIS-Air

Sources

Attribution