Fort Greely Power Plant — Power plant · Oil · Doyon Utilities - Fort Greely
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Fort Greely Power Plant

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Standby
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1959
Net generation, 2025
99 MWh
Grid
25 kV to Golden Valley Elec Assn Inc
Location
Southeast Fairbanks County, Alaska
Operated by
Doyon Utilities - Fort GreelySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Technology
Oil source: “Petroleum Liquids”
Age
67 years since 1959
Heat rate
9,558 Btu/kWh 2025
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Eia status
By code
SB
Mw
7.40
Units
4
Standby mw
7.40
Status rule
majority_mw_standby
In service mw
7.40
Out of service mw
0
Fuel burned (MMBtu), 2025946
Capacity factor, 20250.002
Heat rate (Btu/kWh), 20259,557.5
Net generation (MWh), 202598.98

Retirement

Capacity retired
3 MW
Generators retired
3
Capacity still in service
7.4 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
EN-1Petroleum Liquids1 MWRetiredAugust 2009
EN-2Petroleum Liquids1 MWRetiredAugust 2009
EN-3Petroleum Liquids1 MWRetiredAugust 2009

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
25 kV
Transmission or distribution system owner
Golden Valley Elec Assn Inc
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units EN-1, EN-2, EN-3 scheduled to retire, 3 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

Sources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source