Iowa Methodist Medical Center
Power plant · Oil
Key facts
Power plant · Oil Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1987
- Net generation, 2014
- 0 MWh
- Location
- Polk County, Iowa
- Operated by
- Iowa Methodist Medical Center
Output
- Gas
- Oil
Details
Who’s behind it
Interested in this project?
- Technology
- Oil source: “Petroleum Liquids”
- Age
- 39 years since 1987
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| EPA greenhouse gas reporting (GHGRP) |
|
| Balancing authority code | MISO |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- May 2015
- Capacity retired
- 3.5 MW
- Generators retired
- 3
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| 1 | Petroleum Liquids | 1.5 MW | Retired | May 2015 |
| 2 | Petroleum Liquids | 1.5 MW | Retired | May 2015 |
| 3 | Petroleum Liquids | 0.5 MW | Retired | May 2015 |
Grid
EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).- Balancing authority
- MISO
Transmission lines within 15 mi (10)
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Central Iowa Health Corporation | Owner | 100.0% | Dec 31, 2023 | EPA GHGRP |
| Iowa Methodist Medical Center | Operator | EIA-860M |
Timeline
- Stated Units 1, 2, 3 scheduled to retire, 3.5 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · EIA · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT) · EIA-860M Preliminary Monthly Electric Generator Inventory
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
- EIA-860M Preliminary Monthly Electric Generator Inventory
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| CLOP DES MOINES IA, LLC Built | Large load | 4.1 mi | |
| IOWA HEALTH SYSTEM Built | Large load | 4.3 mi | |
| UNITY POINT HEALTH Built | Large load | 4.3 mi | |
| SE Cor Data Hall (Ankeny data centre) Under construction | Large load | 6.0 mi | |
| MCC IOWA, LLC Built | Large load | 6.2 mi | |
| JORDVERT, LLC Built | Large load | 6.6 mi | |
| DSM 18 (Des Moines data centre) Filed | Large load | 6.7 mi | |
| SICULUS, INC. Built | Large load | 7.6 mi | |
| R & R REALTY Built | Large load | 7.9 mi | |
| EDGED DES MOINES, LLC Built | Large load | 8.4 mi | |
| MICROSOFT CORPORATION - ALLUVIUM DATA CENTER Built | Large load | 10.5 mi | |
| GINGER WEST DATA CENTER Built | Large load | 10.5 mi | |
| Metro Methane Recovery Facility Postponed | Biomass | 14.5 mi | 1.6 |
Sources EPA ICIS-Air · FAA OE/AAA · EIA-860M