Show on map
Kenosha - Albers 138 kV — Transmission lineRed Oak Ridge Energy Center LLC — Studied · Gas, other · WI · 1,211.2 MW · 5.2 mi away2250 (Racine data centre) — Filed · Large load · WI · 5.5 mi awayMICROSOFT CORPORATION - MKE 3B DATA CENTER — Built · Large load · WI · 5.6 mi awayZion Energy Center — Postponed · Gas, combustion turbine · IL · 397.8 MW · 6.0 mi awayNL IL Lake — Under construction · Solar · IL · 5 MW · 6.9 mi awayCenergy IL - Zion Park District — Under construction · Solar · IL · 2.3 MW · 7.0 mi awayMLC 300 (Racine data centre) — Filed · Large load · WI · 7.4 mi awayIL - Renewable Properties - Bobcat - Wes — Under construction · Solar · IL · 4.5 MW · 7.5 mi away
  • Combustion
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Kenosha - Albers 138 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
138 kV
States crossed
US-WI
Owner (as stated)
American Transmission

Details

Who’s behind it

Owner
American Transmission

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Mapped route length (miles)
4
Substations at the ends (as the source names them)
Kenosha to Albers
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itamerican transmission
HIFLD line ID121054
Voltage class100-161 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Red Oak Ridge Energy Center LLC Studied Gas, other 5.2 mi 1,211.2
2250 (Racine data centre) Filed Large load 5.5 mi
MICROSOFT CORPORATION - MKE 3B DATA CENTER Built Large load 5.6 mi
Zion Energy Center Postponed Gas, combustion turbine 6.0 mi 397.8
NL IL Lake Under construction Solar 6.9 mi 5
Cenergy IL - Zion Park District Under construction Solar 7.0 mi 2.3
MLC 300 (Racine data centre) Filed Large load 7.4 mi
IL - Renewable Properties - Bobcat - Wes Under construction Solar 7.5 mi 4.5

Sources EIA-860M · Berkeley Lab · FAA OE/AAA · EPA ICIS-Air

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • Berkeley LabOpen license, with credit · retrieved Nov 4, 2026Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker.
  • FAA OE/AAAOpen license · retrieved Nov 23, 2026
  • EPA ICIS-AirOpen license · retrieved Nov 16, 2026

Attribution