Lower Mount Bethel Energy

Power plant · Gas, combined cycle

Key facts

Power plant · Gas, combined cycleran 79% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2004
Net generation, 2025
4,484,858 MWh
Grid
230 kV to PPL Electric Utilities Corp (PJM)
Location
Northampton County, Pennsylvania

Output

Net generation MWh by year, 2004 to 2026
Fuel burned MMBtu by year, 2004 to 2026
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Technology
Gas, combined cycle source: “Natural Gas Fired Combined Cycle”
Age
22 years since 2004
Unused energy
1,223 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
7,204 Btu/kWh 2025
All 8 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Parents
Name
Lower Mount Bethel Project Co LLC
Share pct
100
Gem entity id
E100000003495
Unit ids
G100000401965
Location id
L100000401575
Eia plant ids
55667
Grid
Nerc region
RFC
Report year
2025
Grid voltage kv
230
Transmission owner
PPL Electric Utilities Corp
Balancing authority code
PJM
Balancing authority name
PJM Interconnection, LLC
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110017810662
Subparts reported
D
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1000146
Fuel burned (MMBtu), 202532,308,154
Capacity factor, 20250.786
Heat rate (Btu/kWh), 20257,203.8
Net generation (MWh), 20254,484,858
Balancing authority codePJM

Ownership

3 companies3
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
TALEN ENERGY CORP Owner 100.0% Dec 31, 2023 EPA GHGRP
Lower Mount Bethel Project Company LLC Owner 100.0% Dec 31, 2025 EIA-860
Lower Mount Bethel Energy LLC Operator EIA-860M

Timeline

  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · EIA · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT) · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Warren County Solar Postponed Solar 0.9 mi 3
PPL Glendon LFGTE Plant Postponed Biomass 11.3 mi 1.6

Sources EIA-860M

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026

Attribution