Osawatomie Power Plant North Sub
- Combustion
- Operating
- 10 · 100 · 1,000 MW
Map
- Combustion
- Operating
Osawatomie Power Plant North Sub: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Osawatomie Power Plant North Sub
Power plant · Oil
Key facts
Power plant · Oilran 0% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2018
- Net generation, 2025
- 3 MWh
- Grid
- 34 kV to City of Osawatomie - (KS) (SWPP)
- Location
- Miami County, Kansas
- Operated by
- City of Osawatomie - (KS)SourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2025
- 3
MWh - Fuel burned, 2025
- 28
MMBtu - Capacity factor, 2025
- 0.0
% - Heat rate, 2025
- 9,333
Btu/kWh
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2025 | 3 | 28 | 0.0% | 9,333 |
| 2024 | 27 | 352 | 0.1% | 13,037 |
| 2023 | 5 | 140 | 0.0% | 28,000 |
| 2022 | 22 | 196 | 0.0% | 8,909 |
| 2021 | 134 | 1,457 | 0.2% | 10,873 |
| 2020 | 11 | 126 | 0.0% | 11,454 |
| 2019 | 25 | 218 | 0.1% | 8,720 |
| 2018 (8 of 12 months) | 0 | 0 | — | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.