Show on map
Project #7 - South Side Landfill Inc. — RNG project · Renewable natural gas · Indy High Btu LLCLILLY LTC-N K323 MODULAR DATA CENTER ADDITION — Built · Large load · IN · 1.9 mi awayDC BLOX INDIANAPOLIS DATA CENTER IND1-A — Under construction · Large load · IN · 8.8 mi away
  • Loads
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Project #7 - South Side Landfill Inc.

RNG project · Renewable natural gas

Key facts

RNG project · Renewable natural gas Operating
Location
Marion County, Indiana
Operated by
Indy High Btu LLCSourceEPA Landfill Methane Outreach Program (LMOP) Landfill and Project Database — landfill gas energy projects (owner/developer, project type, capacity, status)

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Project type
Vehicle Fuel
Technology
Renewable natural gas
LFG flow to project
2.98 MMscf/d
Host landfill
South Side Landfill Inc.
Start year
2020

Capacity not stated

All 11 attributes from EPA Landfill Methane Outreach Program (LMOP) Landfill and Project Database — landfill gas energy projects (owner/developer, project type, capacity, status)
Attributes
AttributeValue
EPA Renewable Fuel Standard registration
RIN D-codes
D3
Company
Indy High BTU LLC
Facility
INDY HIGH BTU LLC
Facility type
Gas/Ethanol, Biogas Producer
Approved pathways
1
Landfills1
Landfill opened1971
Landfill closure year2039
Waste in place (tons)27,693,911
Waste in place, year2022
Landfill design capacity (tons)51,050,160
Landfill gas collected (MMscf/d)4.06
Landfill gas generated (MMscf/d)6.38
Direct emission reductions (MMTCO2e/yr)0.292
Avoided emissions (MMTCO2e/yr)0.024
Data notes (1)
  • First registered not shown: EPA's Part 80 registration list is a current-state snapshot and states no registration or approval date

Timeline

  • In service · EPA LMOP

Around this asset

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
LILLY LTC-N K323 MODULAR DATA CENTER ADDITION Built Large load 1.9 mi
DC BLOX INDIANAPOLIS DATA CENTER IND1-A Under construction Large load 8.8 mi