Show on map
Zion - Pleasant Prairie 345 kV — Transmission lineZion Energy Center — Postponed · Gas, combustion turbine · IL · 397.8 MW · 0.2 mi awayCenergy IL - Zion Park District — Under construction · Solar · IL · 2.3 MW · 0.2 mi awayNL IL Lake — Under construction · Solar · IL · 5 MW · 0.2 mi awayIL - Renewable Properties - Bobcat - Wes — Under construction · Solar · IL · 4.5 MW · 1.6 mi awayRed Oak Ridge Energy Center LLC — Studied · Gas, other · WI · 1,211.2 MW · 7.0 mi away2250 (Racine data centre) — Filed · Large load · WI · 9.2 mi awayMICROSOFT CORPORATION - MKE 3B DATA CENTER — Built · Large load · WI · 9.5 mi awayMLC 300 (Racine data centre) — Filed · Large load · WI · 10.9 mi awayT5 CHI IV Data Center Buildings — Filed · Large load · IL · 13.1 mi awayT5@CHICAGO IV, LP — Built · Large load · IL · 13.3 mi away
  • Combustion
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Zion - Pleasant Prairie 345 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
345 kV
States crossed
US-IL, US-WI
Owner (as stated)
American Transmission

Details

Who’s behind it

Owner
American Transmission

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Mapped route length (miles)
12
Substations at the ends (as the source names them)
Zion to Pleasant Prairie
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itamerican transmission
HIFLD line ID103303
Voltage class345 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Zion Energy Center Postponed Gas, combustion turbine 0.2 mi 397.8
Cenergy IL - Zion Park District Under construction Solar 0.2 mi 2.3
NL IL Lake Under construction Solar 0.2 mi 5
IL - Renewable Properties - Bobcat - Wes Under construction Solar 1.6 mi 4.5
Red Oak Ridge Energy Center LLC Studied Gas, other 7.0 mi 1,211.2
2250 (Racine data centre) Filed Large load 9.2 mi
MICROSOFT CORPORATION - MKE 3B DATA CENTER Built Large load 9.5 mi
MLC 300 (Racine data centre) Filed Large load 10.9 mi
T5 CHI IV Data Center Buildings Filed Large load 13.1 mi
T5@CHICAGO IV, LP Built Large load 13.3 mi

Sources EIA-860M · Berkeley Lab · FAA OE/AAA · EPA ICIS-Air

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • Berkeley LabOpen license, with credit · retrieved Nov 4, 2026Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker.
  • FAA OE/AAAOpen license · retrieved Nov 23, 2026
  • EPA ICIS-AirOpen license · retrieved Nov 16, 2026

Attribution