Bellrock Offshore Wind Farm
Offshore wind
- Capacity
- Capacity: sourceNESO · Open license, with creditMW
- Queue position
- PRO-001496-1, PRO-001496-2
- In-service date
- (stated)
- Location
- Hurlie 400kV substation, United Kingdom
Details
Who’s behind it
- Developer
- Bellrock Offshore Wind Farm Limited
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Kind
- Generation
- Technology
- Offshore wind source: “Wind Offshore”
- Capacity (MW)
- 1,800 Capacity is the sum of the 2 interconnection requests listed under Sources.
- Connects at
- Hurlie 400kV substationConnection point3,408 MW active (3 of 3 projects).
Timeline
- Stated In-service date stated by NESO.
- Observed as filed in NESO (source status: “Scoping”).
About these dates
“Stated” dates are the source’s plan, not a commitment.
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
1 sourceSources NESO
Supported by National Energy SO Open Data