Show on map
Exact site not public
Map
Blue Energy Center- Phase 1a - Gas in Texas: the ring is the region's center, not the site. Outline: Natural Earth and US Census Bureau, both public domain.
Blue Energy Center- Phase 1a - Gas
Gas, combustion turbine
- Capacity
- Capacity: sourceERCOT · Open licenseMW
- Queue position
- 30INR0150
- In-service date
- (stated)
- Location
- Victoria County, Texas (exact site not stated)EstimateEstimated from the county centroid. The source names the county, not the site. Source: ERCOT. How we estimate →
Details
Who’s behind it
- Developer
- Brother 1, LLC
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Kind
- Generation
- Technology
- Gas, combustion turbine source: “Gas - Combustion (gas) Turbine, but not part of a Combined-Cycle”
- Connects at
- Tap 345kV 80286 DULCE7A - 8676 STATIC7AConnection point2,905 MW active (4 of 4 projects).
At this site
2 records at Blue Energy Center- Phase 1a - GasAt this siteGrouped by the same grid connection point and developer. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | Blue Energy Center- Phase 1a - Gas this record | Gas, combustion turbine | 780 | Studied |
| Same site, relation unclear low confidence | Blue Energy Center - Phase 1b – Steam | Gas, combined cycle | 330 | Studied |
Also at this interconnection point (2)
Other requests at the same grid connection point, from another or no named developer. They share the connection, not the site.
- Blue Energy Center - Phase 3 – Steam Stage 2 Nuclear, 1,320 MW, studied at Tap 345kV 80286 DULCE7A - 8676 STATIC7A
- Blue Energy Center - Phase 2b – Steam Gas, steam turbine, 475 MW, studied at Tap 345kV 80286 DULCE7A - 8676 STATIC7A
Sources ERCOT
Timeline
- Stated In-service date stated by ERCOT.
- Observed as studied in ERCOT (source status: “Active”).
About these dates
“Stated” dates are the source’s plan, not a commitment.
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources ERCOT