Show on map
- Wind & solar
- In development
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- In development
Hop Hill Solar Generation and BESS: the source's site coordinate. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Hop Hill Solar Generation and BESS
Solar
Key facts
Solar Filed (source status: (L) Regulatory approvals pending. Not under construction) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Interconnection queue
- Bonneville Power Administration (BPAT)
- In-service date
- (stated)
- Location
- Benton County, Washington
Sources
-
View at source →
EIA-860M · 3 records (68342-HOHI, 68342-HOHI2, 68342-HOHI1)
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain
Units and requests (3)
How these combine
This project is one site. Each row is one unit or request a register lists for it: a generator in EIA-860M, a stage in NESO’s register, a request in a grid queue. Capacity is the live interconnection requests’ MW added up where there are any, plus any listed generator of a technology no request covers; otherwise the generators’ MW added up. The status is the most advanced any row reports; a withdrawn row ends the project only when no other row carries it on.
| Source | Record | Name | Technology | MW | Status | Proposed COD |
|---|---|---|---|---|---|---|
| EIA-860M Generator | 68342-HOHI2 | Hop Hill Solar Generation and BESS | Storage | 500 | Filed “(L) Regulatory approvals pending. Not under construction” | Sep 1, 2031 |
| EIA-860M Generator | 68342-HOHI1 | Hop Hill Solar Generation and BESS | Solar | 500 | Filed “(L) Regulatory approvals pending. Not under construction” | Sep 1, 2031 |
| EIA-860M Generator | 68342-HOHI | Hop Hill Solar Generation and BESS | Wind | 200 | Filed “(L) Regulatory approvals pending. Not under construction” | Sep 1, 2031 |