LNH INC DBA HOSTING.COM - 350 PENCADER: the source's site coordinate and 5 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
LNH Inc DBA Hosting.COM - 350 Pencader
Data center
As filed: LNH INC DBA HOSTING.COM - 350 PENCADER
- Kind
- Data center
- Location
- New Castle County, Delaware
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
- Kind
- Data center source: “Data Center”
- Capacity (MW)
- Not stated
- Selected as a data center because its industry code is NAICS 518210 (data processing and hosting). Some sites with this code are offices with a server room: 39 of 49 checked by hand were data centers. EPA ECHO ICIS-Air national facility download (data-centre selection, placed through FRS)
At this site
2 records at LNH INC DBA HOSTING.COM - 350 PENCADERAt this siteGrouped by the same exact location and project name. The lead is the largest active filing. Each record keeps its own page.
| Relationship | Name | Technology | MW | Status |
|---|---|---|---|---|
| Lead filing | LNH INC DBA HOSTING.COM - 350 PENCADER this record | Large load | — | Built |
| Another phase high confidence | LNH INC DBA HOSTING.COM - 650 PENCADER | Large load | — | Built |
Sources EPA ICIS-Air
Timeline
- Observed as built in EPA ICIS-Air (source status: “Operating”).
About these dates
“Stated” dates are the source’s plan, not a commitment.
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources EPA ICIS-Air
Local government activity · LocalGovIndex Meeting records by GovData Systems
Around this project
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| LNH INC DBA HOSTING.COM - 650 PENCADER Built | Large load | 0.1 mi | |
| JP MORGAN CHASE - BEAR CHRISTIANA ROAD Built | Large load | 6.1 mi | |
| DXC TECHNOLOGY SERVICES LLC Built | Large load | 7.2 mi | |
| Deepwater Postponed | Gas, combustion turbine | 14.3 mi | 456 |
| ENGIE Solidago Solar Project - Hybrid Announced | Storage | 15.0 mi | 12.5 |
Sources EPA ICIS-Air · EIA-860M