North Edinburg BESS 1
- Storage
- Under construction
- Operating
- 10 · 100 · 1,000 MW
Map
- Storage
- Under construction
- Operating
North Edinburg BESS 1: the source's site coordinate and 2 exact-grade projects within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
North Edinburg BESS 1
Battery storage
Key facts
Battery storage Under construction (source status: (V) Under construction, more than 50 percent complete) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- In-service date
- (stated)
- Location
- Hidalgo County, Texas
Details
Who’s behind it
- Developer
- Edinburg ESS Assets LLC
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Kind
- Storage source: “Batteries”
- EIA plant
- 69253 generator NEBA1
Timeline
- Observed as under construction in EIA-860M (source status: “(V) Under construction, more than 50 percent complete”).
- Stated In-service date stated by EIA-860M.
About these dates
“Stated” dates are the source’s plan, not a commitment.
Status and dates as the source last listed them. Later changes follow as we see them.
Sources
1 sourceSources EIA-860M
Around this project
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Gunnar Reliability Project Built | Storage | 3.3 mi | 154.8 |
| Jerboa Storage Postponed | Storage | 9.4 mi | 200 |