Project FluxNet Solar SLF

Solar + storage

Capacity
Capacity: sourceERCOT · Open licenseMW
Queue position
29INR0238, 29INR0239
In-service date
(stated)
Location
Jones County, Texas (exact site not stated)EstimateEstimated from the county centroid. The source names the county, not the site. Source: ERCOT. How we estimate →

Details

Who’s behind it

Interested in this project?

Set an alert
More Book a call Join the beta
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
Kind
Generation
Technology
Solar + storage source: “Solar - Photovoltaic Solar + Other - Battery Energy Storage”
Capacity (MW)
334.7 Capacity is the sum of the 2 interconnection requests listed under Sources.
Connects at
tap 345kV 60514 Clear Crossing - 11419 Coody CrossConnection point608.1 MW active (2 of 2 projects).

Timeline

  • Stated In-service date stated by ERCOT.
  • Observed as studied in ERCOT (source status: “Active”).
  • First published from ERCOT GIS Report (Generator Interconnection Status).
About these dates

“Stated” dates are the source’s plan, not a commitment.

Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.

Sources

1 source

Sources ERCOT

Sources

  • ERCOTOpen license · retrieved Nov 4, 2026