Selenite Springs Solar: the source's site coordinate and 1 exact-grade project within 15 mi. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Selenite Springs Solar
Solar
- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Queue position
- 29INR0147
- In-service date
- (stated)
- Location
- Pecos County, Texas
Details
Who’s behind it
- Developer
- NextEra Energy Resources - ERCOT · part of NextEra EnergyOwnership claimOwnership link recorded from the companies' own published statements; no date stated by the source.
Interested in this project?
Set an alert
About these actionsOur team gets you what you need. Beta: private project space · data room · readiness check Want this as data? Free via the API and alerts.
- Kind
- Generation
- Technology
- Solar source: “Solar - Photovoltaic Solar”
- Capacity (MW)
- 253 Capacity is the interconnection request in ERCOT GIS Report (Generator Interconnection Status). The 1 generator listed in EIA-860M Preliminary Monthly Electric Generator Inventory (listed under Sources) total 250 MW nameplate.
- Connects at
- Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching StationConnection point653 MW active (2 of 2 projects).
- EIA plant
- 70047 generator SSPV
Timeline
- Stated In-service date stated by ERCOT.
- Observed as contracted in ERCOT (source status: “Completed”).
About these dates
“Stated” dates are the source’s plan, not a commitment.
Status: the most advanced any source reports, dated by that source. Later changes follow as we see them.
Sources
2 sourcesAround this project
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Bighorn Ridge Solar Permitted | Solar | 3.0 mi | 300 |
Sources EIA-860M