Show on map
- Combustion
- Under construction
- 10 · 100 · 1,000 MW
Map
- Combustion
- Under construction
Shady Hills Combined Cycle Facility: the source's site coordinate. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Shady Hills Combined Cycle Facility
Gas, combined cycle
Key facts
Gas, combined cycle Under construction (source status: (TS) Construction complete, but not yet in commercial operation) (what this status means)- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Interconnection queue
- Duke Energy Florida (FPC)
- In-service date
- (stated)
- Location
- Pasco County, Florida
Sources
-
View at source →
EIA-860M ·
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain