Wildcat Solar Power Plant LLC

overdue by 3.6 years (target May 1, 2023)

Solar + storage

Capacity
Capacity: sourceLBNL "Queued Up" project-level interconnection queue data file (non-ISO regions) · Open license, with creditMW
Interconnection queue
Public Service Company of New Mexico
Queue position
IA-PNM-2020-12
In-service date
(stated)
Location
McKinley County, New Mexico

Sources

  • Berkeley Lab ·

    LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)

    Open license, with credit · retrieved Nov 4, 2026

    Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker. · license

    Publication page https://eta-publications.lbl.gov/publications/queued-2026-edition-characteristics, retrieved 2026-10-23 (HTTP 200) — "Copyright Notice: The Queued Up data file is licensed CC BY 4.0. You may use, share, or adapt the dataset as long as you attribute it to Lawrence Berkeley National Laboratory and GridTracker." and "Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker. CC BY 4.0. All rights reserved." The file's Introduction sheet adds the DOE contract notice ("This dataset has been authored by an author at Lawrence Berkeley National Laboratory under Contract No. DE-AC02-05CH11231 with the U.S. Department of Energy ...") and the standard no-warranty disclaimer

    View at source →
  • EIA-860M · 2 records (64849-ATMWS, 64849-WILDC)

    EIA-860M Preliminary Monthly Electric Generator Inventory

    Open license · retrieved Nov 4, 2026

    US federal work — public domain

    View at source →
Units and requests (3)
Units and requests that make up this project
SourceRecordNameTechnologyMWStatusProposed COD
LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions) Request PNM/IA-PNM-2020-12 Wildcat Solar Power Plant Solar + storage 90 Filed “suspended” May 1, 2023
EIA-860M Generator 64849-WILDC Wildcat Solar Power Plant LLC Solar 90 Announced “(P) Planned for installation, but regulatory approvals not initiated” Dec 1, 2028
EIA-860M Generator 64849-ATMWS Wildcat Solar Power Plant LLC Storage 50 Announced “(P) Planned for installation, but regulatory approvals not initiated” Dec 1, 2028
Report a problem
What is wrong with Wildcat Solar Power Plant LLC?

Up to 2,000 characters. A link to a source helps an editor check it.

Only if you would like a reply. It is used for this report and nothing else; see the privacy notice.

Sources

Sources Berkeley Lab

Sources

  • Berkeley LabOpen license, with credit · retrieved Nov 4, 2026Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker.

Attribution

View at source