Lake Clementine Hydroelectric C7

Site of 2 records

Company not recorded

Lead filing
LAKE CLEMENTINE HYDROELECTRIC C7
Grouped by
the same grid connection point and project name
Active (MW)
0 across 0
Built (MW)
0 across 0
Withdrawn or canceled (MW)
31 across 2
EIA plant ID
—
Connects at
Halsey Substation 60 kV
Operating plant
—

1. Records at this site

Records at this site: the lead first; each EIA plant's units follow its first unit; every other record with its relationship to the lead, its confidence, technology, capacity, status and company.
RelationshipConfidenceNameTechnologyMWStatusCompany
Lead filing — LAKE CLEMENTINE HYDROELECTRIC C7 Hydro 15.5 Withdrawn —
Earlier filing, superseded low LAKE CLEMENTINE HYDROELECTRIC Hydro 15.5 Withdrawn —

2. Also at this interconnection point

None recorded.

3. Sources

Sources CAISO

Sources

Attribution