Alburtis 230 kV line — Transmission lineTIERPOINT TWO, LLC - TEKPARK FACILITY — Built · Large load · PA · 5.9 mi awayMaidencreek Biomass Plant — Postponed · Biomass · PA · 5.2 MW · 10.7 mi awayPioneer Crossing Energy, LLC — Postponed · Biomass · PA · 3.2 MW · 11.5 mi away
  • Loads
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Alburtis 230 kV line

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
230 kV
States crossed
US-PA

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
16
Substations at the ends (as the source names them)
Alburtis
All 2 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
HIFLD line ID118464
Voltage class220-287 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
TIERPOINT TWO, LLC - TEKPARK FACILITY Built Large load 5.9 mi
Maidencreek Biomass Plant Postponed Biomass 10.7 mi 5.2
Pioneer Crossing Energy, LLC Postponed Biomass 11.5 mi 3.2

Sources EPA ICIS-Air · EIA-860M

Sources

Attribution