Arbuckle: route and 36 exact-grade projects within 25 km. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Arbuckle
HGL pipeline
Key facts
HGL pipeline Operating- Mapped route length
- Mapped route length: sourceEIA Energy Atlas · Open licensemiles
- States crossed
- US-KS, US-TX
- Operated by
- ONEOKSourceEIA US Energy Atlas — Hydrocarbon Gas Liquids (HGL) Pipelines (line geometries, operator, pipeline name)
Details
Who’s behind it
No companies named in filings yet.
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Mapped route length (miles)
- 595
- Units
- 1
All 5 attributes from EIA US Energy Atlas — Hydrocarbon Gas Liquids (HGL) Pipelines (line geometries, operator, pipeline name)
| Attribute | Value |
|---|---|
| Mapped parts | 1 |
| Operator, as the source states it | ONEOK |
| Mapped segments | 1 |
| Source release | 202001 |
| Pipeline name raw | Arbuckle |
Sources
2 sourcesSources EIA Energy Atlas · EIA US Energy Atlas — Hydrocarbon Gas Liquids (HGL) Pipelines (line geometries, operator, pipeline name)
Sources
- EIA US Energy Atlas — Hydrocarbon Gas Liquids (HGL) Pipelines (line geometries, operator, pipeline name)Source: U.S. Energy Information Administration, U.S. Energy Atlas, HGL Pipelines (as of January 2020)
- EIA US Energy Atlas — Hydrocarbon Gas Liquids (HGL) Pipelines (line geometries, operator, pipeline name)
Around this pipeline
Nearby
within 25 km| Project | Kind | Away | MW |
|---|---|---|---|
| Steelhead Energy Storage Studied | Storage | 0.3 km | 192.1 |
| Building (Stillwater data centre) Filed | Large load | 0.4 km | |
| Mcgee Storage Postponed | Storage | 0.5 km | 151.3 |
| Palestine Power Peaking Facility Postponed | Gas, combustion turbine | 2.2 km | 200 |
| Lone Star Power Station Studied | Gas, other | 3.4 km | 478 |
| Halyard Henderson Energy Center Postponed | Gas, combustion turbine | 5.4 km | 464 |
| Sooner Postponed | Coal | 6.9 km | 950 |
| Solex Ridge Solar Filed | Solar | 7.0 km | 100 |
| Willow Creek Energy Storage Under construction | Storage | 7.1 km | 200 |
| Coneflower Storage Project LLC Contracted | Storage | 7.5 km | 170.8 |
| Noor Solar Filed | Solar | 8.1 km | 188.2 |
| Hallmark Postponed | Solar | 8.2 km | 42 |
| Crockett Postponed | Storage | 8.5 km | 9.9 |
| Ripley Energy Center Under construction | Gas, combustion turbine | 9.9 km | 419 |
| Ponca City Refinery Postponed | Gas, other | 10.8 km | 5 |
| Triune Solar Announced | Solar | 12.0 km | 100 |
| Majors DC Site – Data Center Building #1 Filed | Large load | 12.2 km | |
| Cedar Range Solar Contracted | Solar | 12.2 km | 150.6 |
| Willis Storage Contracted | Storage | 13.6 km | 176.1 |
| GCCISD NEW TECHNOLOGY DATA CENTER Unknown | Large load | 15.5 km | |
| Old Jackson Solar LLC Postponed | Solar | 17.3 km | 128 |
| Mcmurtre Storage Contracted | Storage | 17.6 km | 177.6 |
| Cedar Bayou 5 Under construction | Gas, combustion turbine | 18.0 km | 697 |
| Valley (TX) Postponed | Coal | 18.5 km | 800 |
| Neches Station, LLC Postponed | Gas, combustion turbine | 19.1 km | 464 |
| Chilocco Wind Farm Postponed | Wind | 19.9 km | 169.2 |
| Viola Generating Station Permitted | Gas, combined cycle | 20.1 km | 765 |
| Mullin Creek #1 Generating Station Permitted | Gas, combustion turbine | 21.6 km | 489.7 |
| McNew Generating Station Permitted | Gas, combined cycle | 21.6 km | 765 |
| Houston County BESS Studied | Storage | 21.8 km | 125.4 |
| Lupinus Solar 1, LLC Under construction | Solar + storage | 22.2 km | 246.3 |
| Lupinus Solar 2, LLC Contracted | Solar + storage | 22.2 km | 366.9 |
| Brotherton Storage Contracted | Storage | 22.5 km | 176.1 |
| Lucky 7 Solar Farm LLC Under construction | Solar | 22.5 km | 101.3 |
| Amador BESS Under construction | Storage | 24.1 km | 102.4 |
| Forest Grove - Dodd Postponed | Solar + storage | 24.4 km | 302 |
Sources ERCOT · EIA-860M · FAA OE/AAA · Berkeley Lab · EPA ICIS-NPDES
Sources
- ERCOT GIS Report (Generator Interconnection Status)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- FAA OE/AAA Part 77 obstruction evaluation case archives (data-centre sites, buildings and cranes)
- LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker.
- EPA ECHO ICIS-NPDES construction stormwater coverage (data-centre sites, national)