Aspen Biomass Power Plant — Power plant · Biomass · Aspen Power LLCPinecrest Energy Center — Postponed · Gas, combined cycle · TX · 753 MW · 2.9 mi awaySun Angel ESS — Studied · Storage · TX · 201.5 MW · 4.7 mi awayBanita Creek- Spindlepop Solar — Under construction · Solar + storage · TX · 673.9 MW · 13.4 mi away
  • Wind & solar
  • Storage
  • Bioenergy
  • In development
  • Under construction
  • Retired
  • 10 · 100 · 1,000 MW

Aspen Biomass Power Plant

Power plant · Biomass

Key facts

Power plant · Biomassran 10% of 2014 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2011
Net generation, 2014
38,478 MWh
Location
Angelina County, Texas
Operated by
Aspen Power LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2010 to 2015
Fuel burned MMBtu by year, 2010 to 2015
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Wood/Wood Waste Biomass”
Age
15 years since 2011
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeERCO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
September 2015
Capacity retired
44 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN7Wood/Wood Waste Biomass44 MWRetiredSeptember 2015

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
ERCO
Transmission lines within 15 mi (10)
Connection points within 15 mi (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit GEN7 scheduled to retire, 44 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · OpenStreetMap · ERCOT · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

© OpenStreetMap contributors

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • OpenStreetMapOpen license, with credit · retrieved Oct 10, 2026© OpenStreetMap contributors. Power lines, cables and substations filtered and reshaped by Inframation from the OpenStreetMap elements in Overture Maps' base/infrastructure theme; this derived database is available under the Open Database License 1.0 as GeoParquet files at https://tiles.inframation.io/grid/osm-power/ (latest.json names the current version's files; licence: https://www.openstreetmap.org/copyright)
  • ERCOTOpen license · retrieved Nov 4, 2026
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Pinecrest Energy Center Postponed Gas, combined cycle 2.9 mi 753
Sun Angel ESS Studied Storage 4.7 mi 201.5
Banita Creek- Spindlepop Solar Under construction Solar + storage 13.4 mi 673.9

Sources EIA-860M · ERCOT