Show on map
Babcock 345 kV line — Transmission lineLPO DC CAMPUS — Under construction · Large load · IN · 3.3 mi awayDATA CENTER — Built · Large load · IN · 6.2 mi awayHOBART DATA CENTER MASS GRADING - 1 — Under construction · Large load · IN · 9.5 mi awayCrawler Crane (Michigan City data centre) — Filed · Large load · IN · 10.0 mi awayMerrillville Solar — Announced · Solar · IN · 100 MW · 10.1 mi awayLAVENDER FIELDS HOLDINGS LLC — Built · Large load · IN · 10.1 mi awayAMAZON DATA SERVICES INCORPORATED — Built · Large load · IN · 12.1 mi awaySt Joseph Energy Center — Postponed · Gas, combined cycle · IN · 1,406 MW · 12.2 mi awayChampion Solar I — Postponed · Solar · IN · 51.9 MW · 13.3 mi away
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Babcock 345 kV line

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
345 kV
States crossed
US-IN
Owner (as stated)
Northern Indiana Public Service

Details

Who’s behind it

Owner
Northern Indiana Public Service

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
29
Substations at the ends (as the source names them)
Babcock
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itnorthern indiana public service
HIFLD line ID120543
Voltage class345 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
LPO DC CAMPUS Under construction Large load 3.3 mi
DATA CENTER Built Large load 6.2 mi
HOBART DATA CENTER MASS GRADING - 1 Under construction Large load 9.5 mi
Crawler Crane (Michigan City data centre) Filed Large load 10.0 mi
Merrillville Solar Announced Solar 10.1 mi 100
LAVENDER FIELDS HOLDINGS LLC Built Large load 10.1 mi
AMAZON DATA SERVICES INCORPORATED Built Large load 12.1 mi
St Joseph Energy Center Postponed Gas, combined cycle 12.2 mi 1,406
Champion Solar I Postponed Solar 13.3 mi 51.9

Sources EPA ICIS-NPDES · FAA OE/AAA · EIA-860M · EPA ICIS-Air

Sources

Attribution