Basin — Crude oil pipeline · PLAINS ALL AMERICAN PIPELINEFGE Texas II — Gas, combined cycle · TX · 743 MW · 0.7 km awayFGE Texas I — Gas, combined cycle · TX · 743 MW · 0.8 km awayBARBER LAKE DATA CENTER PROJECT — Large load · TX · 2.3 km awayDolce BESS, LLC — Storage · TX · 100.7 MW · 2.5 km awayRush Springs Solar — Solar · OK · 200 MW · 3.3 km awayQuick Draw — Wind · TX · 174 MW · 3.8 km awayGBG SOLAR — Solar · TX · 22.2 MW · 5.7 km awayHackberry Creek Solar — Solar · TX · 175.5 MW · 5.8 km awayMorgan Creek — Coal · TX · 800 MW · 6.0 km awayHorseshoe Lake — Gas, combustion turbine · OK · 896 MW · 6.2 km awaySwenson Solar — Solar · TX · 600 MW · 6.7 km awayTip Top Solar Energy Center LLC — Solar · NM · 220 MW · 7.1 km awayMillers Branch Solar — Solar · TX · 133 MW · 7.1 km awayGaines County — Gas, combustion turbine · TX · 225 MW · 9.5 km awayByers Wind — Wind · TX · 200 MW · 12.0 km awayJayhawk — Solar · TX · 101 MW · 12.7 km awayAC Ranch I — Solar · NM · 75 MW · 13.0 km awayAC Ranch II — Solar · NM · 230 MW · 13.0 km awayGrey Wolf — Gas, combustion turbine · TX · 10 MW · 13.0 km awayThrockmorton Wind — Wind · TX · 225.6 MW · 13.4 km awayDATA CENTER PHASE 1 - EARLY WORKS PACKAGE — Large load · TX · 13.4 km awayBhalu — Storage · TX · 205.5 MW · 13.4 km awayWallie Storage — Storage · TX · 200 MW · 13.9 km awayTexas Clean Energy Project — Gas, other · TX · 400 MW · 15.2 km awayWT2 — Gas, combustion turbine · TX · 10 MW · 15.4 km awayBriggs Solar, LLC — Solar + storage · TX · 659.7 MW · 15.6 km awayQuantum II Solar — Solar · TX · 362.8 MW · 15.7 km awayQuantum II BESS — Storage · TX · 422.4 MW · 15.8 km awayFlatland Solar — Solar · TX · 180 MW · 16.9 km awayCannibal Draw Solar and Storage — Solar + storage · TX · 248.1 MW · 18.6 km awayAlira — Solar · TX · 222.8 MW · 18.8 km awayMonarch Creek Wind, LLC — Wind · TX · 283.4 MW · 18.8 km awayRockhound A — Solar · TX · 245 MW · 20.0 km awayRockhound C — Solar · TX · 61 MW · 20.0 km awayRed Hollow Renewable Energy — Solar + storage · TX · 608.6 MW · 20.5 km awayStonewall BESS — Solar + storage · TX · 195.2 MW · 21.0 km awayHoney Mesquite Wind, LLC — Wind · TX · 180.5 MW · 21.1 km awayZSS Solar — Solar · TX · 450 MW · 21.4 km awayCotton Belle Solar — Solar · TX · 80 MW · 22.1 km awayCunningham Solar II — Solar · NM · 196 MW · 22.3 km awayChampaign BESS, LLC — Storage · TX · 201.1 MW · 22.4 km awayRipley Energy Center — Gas, combustion turbine · OK · 419 MW · 22.7 km awayRockhound D — Solar · TX · 28 MW · 24.1 km away
  • Combustion
  • Wind & solar
  • Storage
  • Loads
  • In development
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Crude oil pipeline

Key facts

Crude oil pipeline Operating
Mapped route length
Mapped route length: sourceEIA Energy Atlas · Open licensemiles
States crossed
US-NM, US-OK, US-TX
Operated by
Plains All American PipelineSourceEIA US Energy Atlas — Crude Oil Pipelines (line geometries, operator, pipeline name)

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
632
Units
2
All 5 attributes from EIA US Energy Atlas — Crude Oil Pipelines (line geometries, operator, pipeline name)
Attributes
AttributeValue
Mapped parts2
Operator, as the source states itPLAINS ALL AMERICAN PIPELINE
Mapped segments2
Source release202001
Pipeline name rawBasin

Sources

2 sources

View at source

Around this pipeline

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
FGE Texas II Postponed Gas, combined cycle 0.7 km 743
FGE Texas I Postponed Gas, combined cycle 0.8 km 743
BARBER LAKE DATA CENTER PROJECT Under construction Large load 2.3 km
Dolce BESS, LLC Studied Storage 2.5 km 100.7
Rush Springs Solar Under construction Solar 3.3 km 200
Quick Draw Postponed Wind 3.8 km 174
GBG SOLAR Under construction Solar 5.7 km 22.2
Hackberry Creek Solar Contracted Solar 5.8 km 175.5
Morgan Creek Postponed Coal 6.0 km 800
Horseshoe Lake Under construction Gas, combustion turbine 6.2 km 896
Swenson Solar Under construction Solar 6.7 km 600
Tip Top Solar Energy Center LLC Under construction Solar 7.1 km 220
Millers Branch Solar Built Solar 7.1 km 133
Gaines County Postponed Gas, combustion turbine 9.5 km 225
Byers Wind Postponed Wind 12.0 km 200
Jayhawk Postponed Solar 12.7 km 101
AC Ranch I Under construction Solar 13.0 km 75
AC Ranch II Filed Solar 13.0 km 230
Grey Wolf Under construction Gas, combustion turbine 13.0 km 10
Throckmorton Wind Under construction Wind 13.4 km 225.6
DATA CENTER PHASE 1 - EARLY WORKS PACKAGE Under construction Large load 13.4 km
Bhalu Studied Storage 13.4 km 205.5
Wallie Storage Postponed Storage 13.9 km 200
Texas Clean Energy Project Postponed Gas, other 15.2 km 400
WT2 Under construction Gas, combustion turbine 15.4 km 10
Briggs Solar, LLC Contracted Solar + storage 15.6 km 659.7
Quantum II Solar Under construction Solar 15.7 km 362.8
Quantum II BESS Under construction Storage 15.8 km 422.4
Flatland Solar Filed Solar 16.9 km 180
Cannibal Draw Solar and Storage Contracted Solar + storage 18.6 km 248.1
Alira Filed Solar 18.8 km 222.8
Monarch Creek Wind, LLC Under construction Wind 18.8 km 283.4
Rockhound A Under construction Solar 20.0 km 245
Rockhound C Under construction Solar 20.0 km 61
Red Hollow Renewable Energy Studied Solar + storage 20.5 km 608.6
Stonewall BESS Studied Solar + storage 21.0 km 195.2
Honey Mesquite Wind, LLC Under construction Wind 21.1 km 180.5
ZSS Solar Permitted Solar 21.4 km 450
Cotton Belle Solar Postponed Solar 22.1 km 80
Cunningham Solar II Permitted Solar 22.3 km 196
Champaign BESS, LLC Contracted Storage 22.4 km 201.1
Ripley Energy Center Under construction Gas, combustion turbine 22.7 km 419
Rockhound D Under construction Solar 24.1 km 28