Borden Chemicals Plastics Cogen

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1985
Net generation, 2004
0 MWh
Location
Ascension County, Louisiana
Operated by
Borden Chemicals & PlasticsSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2004
Fuel burned MMBtu by year, 2001 to 2004
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Age
41 years since 1985

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2005
Capacity retired
103.6 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN1Natural Gas Fired Combustion Turbine26 MWRetiredDecember 2005
GEN2Natural Gas Fired Combustion Turbine38.8 MWRetiredDecember 2005
GEN3Natural Gas Fired Combustion Turbine38.8 MWRetiredDecember 2005

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Transmission lines within 15 mi (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units GEN1, GEN2, GEN3 scheduled to retire, 103.6 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source