Bowater Newsprint Calhoun Operation

Power plant · Biomass

Key facts

Power plant · Biomass Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1954
Net generation, 2023
0 MWh
Location
McMinn County, Tennessee

Output

Net generation MWh by year, 2001 to 2023
Fuel burned MMBtu by year, 2001 to 2023
  • Gas
  • Coal
  • Biomass and waste

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Wood/Wood Waste Biomass”
Age
72 years since 1954
All 3 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Parents
Name
Paper Excellence BV
Share pct
100
Gem entity id
E100002000600
Unit ids
G100001054055, G100001093962, G100001093963
Location id
L100001047480
Eia plant ids
50956
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110056955157
Subparts reported
C, TT
NAICS code
322120
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1000311
Balancing authority codeTVA

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
May 2022
Capacity retired
63.2 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN1Wood/Wood Waste Biomass19 MWRetiredMay 2022
GEN2Wood/Wood Waste Biomass19.2 MWRetiredMay 2022
GEN3Wood/Wood Waste Biomass25 MWRetiredMay 2022

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
TVA
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Resolute Forest Products Operator EIA-860M
RESOLUTE FP US INC Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Units GEN1, GEN2, GEN3 scheduled to retire, 63.2 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · GEM · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Sources

Every source and license · Attribution

View at source