Show on map
Brandon Station — Power plant · Gas, combustion turbine · City of Lubbock - (TX)
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Brandon Station

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbineran 12% of 2023 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1990
Net generation, 2023
21,734 MWh
Location
Lubbock County, Texas

Output

Net generation MWh by year, 2001 to 2023
Fuel burned MMBtu by year, 2001 to 2023
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Age
36 years since 1990
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110071161068
Subparts reported
C
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1006602
Balancing authority codeSWPP

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
October 2023
Capacity retired
21 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Natural Gas Fired Combustion Turbine21 MWRetiredOctober 2023

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
SWPP
Transmission lines within 15 mi (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
City of Lubbock - (TX) Operator EIA-860M
CITY OF LUBBOCK TEXAS TEXAS Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Unit 1 scheduled to retire, 21 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · OpenStreetMap · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

© OpenStreetMap contributors

Sources

Every source and license · Attribution

View at source