Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1948
Net generation, 2025
92 MWh
Grid
69 kV to Ameren Illinois Company (MISO)
Location
White County, Illinois
Operated by
City of Carmi - (IL)SourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
78 years since 1948
Unused energy
117 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
10,587 Btu/kWh 2025
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 2025974
Capacity factor, 20250.001
Heat rate (Btu/kWh), 202510,587
Net generation (MWh), 202592
Balancing authority codeMISO

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
4 MW
Generators retired
3
Capacity still in service
13.4 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
5Natural Gas Internal Combustion Engine0.6 MWRetiredJuly 2013
6Petroleum Liquids0.7 MWRetiredMay 2014
11Petroleum Liquids2.7 MWRetiredDecember 2019
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Petroleum Liquids3.4 MW
Natural Gas Internal Combustion Engine0.6 MW

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
Ameren Illinois Company
Balancing authority
Midcontinent Independent Transmission System Operator, Inc..
NERC region
SERC
Transmission lines within 25 km (4)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit 11 scheduled to retire, 2.7 MW · EIA-860M
  • Stated Unit 6 scheduled to retire, 0.7 MW · EIA-860M
  • Stated Unit 5 scheduled to retire, 0.6 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Norris City 2 Permitted Solar 12.8 km 3.2
Meadow Springs Renewable Energy (Hybrid) Announced Solar + storage 13.0 km 300
Pawpaw (IL) Under construction Solar 23.2 km 5

Sources EIA-860M

Sources

Attribution