Celanese — Power plant · Other · Southwestern Public Service CoIP Meitner Solar — Solar · TX · 500 MW · 20.3 km awayPKN Data Center — Large load · TX · 21.1 km away
  • Wind & solar
  • Unspecified fuel
  • Loads
  • In development
  • Retired
  • Size not stated
  • 10 · 100 · 1,000 MW

Power plant · Other

Key facts

Power plant · Other Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1964
Net generation, 2010
0 MWh
Grid
69 kV to Southwestern Public Service Co (SWPP)
Location
Gray County, Texas
Operated by
Southwestern Public Service CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2003 to 2010
Fuel burned MMBtu by year, 2003 to 2010
  • Gas
  • Unspecified fuel

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Other source: “All Other”
Age
62 years since 1964
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeSWPP

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2010
Capacity retired
50 MW
Generators retired
2
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1All Other13 MWRetiredDecember 2010
2All Other37 MWRetiredDecember 2010

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
Southwestern Public Service Co
Balancing authority
Southwest Power Pool
NERC region
MRO
Transmission lines within 25 km (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2 scheduled to retire, 50 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · OpenStreetMap · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

© OpenStreetMap contributors

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
IP Meitner Solar Filed Solar 20.3 km 500