Centennial — Power plant · Oil · Metlakatla Power & Light
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Oil

Key facts

Power plant · Oil Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2017
Net generation, 2025
-367 MWh
Grid
12 kV to Metlakatla Power & Light
Location
Prince of Wales Ketchikan County, Alaska
Operated by
Metlakatla Power & LightSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2002 to 2025
Fuel burned MMBtu by year, 2002 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
9 years since 2017
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 20252,917
Net generation (MWh), 2025-367
Data notes (2)
  • Capacity factor, 2025 not shown: net generation -367.0 MWh is not positive (the plant consumed at least as much as it produced over the year)
  • Heat rate (Btu/kWh), 2025 not shown: fuel burned but net generation is not positive

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
3.3 MW
Generators retired
1
Capacity still in service
1.8 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
IC6Petroleum Liquids3.3 MWRetiredDecember 2022

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
12 kV
Transmission or distribution system owner
Metlakatla Power & Light
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit IC6 scheduled to retire, 3.3 MW · EIA-860M
  • In service · EIA-860M

Sources

3 sources

View at source