Chamberlain Wind Project

Power plant · Wind

Key facts

Power plant · Wind Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2001
Net generation, 2023
0 MWh
Grid
69 kV to East River Elec Pwr Coop, Inc (SWPP)
Location
Brule County, South Dakota
Operated by
Basin Electric Power CoopSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2023

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Wind source: “Onshore Wind Turbine”
Age
25 years since 2001
All 2 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100001019914, G100001022699
Location id
L100001017925
Eia plant ids
7974
Balancing authority codeSWPP

Wind turbines

Turbines
2
Turbine capacity (MW)
2.6
Turbine models
2 Nordex N60
Hub height (m)
60
Rotor diameter (m)
60
Year online
2001

Source U.S. Wind Turbine Database

Source

  • U.S. Wind Turbine DatabaseOpen license · retrieved 25 Oct 2026Map services and data are available from U.S. Wind Turbine Database, provided by the U.S. Geological Survey, American Clean Power Association, and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uswtdb

Attribution

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
October 2023
Capacity retired
2.6 MW
Generators retired
2
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
WTC1Onshore Wind Turbine1.3 MWRetiredOctober 2023
WTC2Onshore Wind Turbine1.3 MWRetiredOctober 2023

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
East River Elec Pwr Coop, Inc
Balancing authority
Southwest Power Pool
NERC region
MRO
Transmission lines within 25 km (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units WTC1, WTC2 scheduled to retire, 2.6 MW · EIA-860M
  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · LBNL · U.S. Wind Turbine Database · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source