Show on map
Chisago - King Plant 345 kV — Transmission lineNovel Holmquist Solar CSG — Postponed · Solar · MN · 1 MW · 0.1 mi awayNorth Star Energy Storage, LLC — Under construction · Storage · MN · 80 MW · 1.3 mi awayHB FULLER CO - DATA CENTER - ARDEN HILLS — Built · Large load · MN · 11.7 mi away
  • Storage
  • Loads
  • Under construction
  • Operating
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Chisago - King Plant 345 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
345 kV
States crossed
US-MN
Owner (as stated)
Northern States Power Minnesota

Details

Who’s behind it

Owner
Northern States Power Minnesota

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
38
Substations at the ends (as the source names them)
Chisago to King Plant
All 3 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
Owner, as the source states itnorthern states power minnesota
HIFLD line ID114090
Voltage class345 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Novel Holmquist Solar CSG Postponed Solar 0.1 mi 1
North Star Energy Storage, LLC Under construction Storage 1.3 mi 80
HB FULLER CO - DATA CENTER - ARDEN HILLS Built Large load 11.7 mi

Sources EIA-860M · EPA ICIS-Air

Sources

Attribution