Collins Pine Project

Power plant · Biomass

Key facts

Power plant · Biomassran 35% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2021
Net generation, 2025
15,288 MWh
Grid
60 kV to Pacific Gas & Electric Co (CISO)
Location
Plumas County, California
Operated by
Collins Pine CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Wood/Wood Waste Biomass”
Age
5 years since 2021
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 2025574,658
Capacity factor, 20250.349
Net generation (MWh), 202515,288.0
Balancing authority codeCISO
Data notes (1)
  • Heat rate (Btu/kWh), 2025 not shown: computed 37588.9 outside 5000-30000 Btu/kWh

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
12 MW
Generators retired
1
Capacity still in service
5 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GEN4Wood/Wood Waste Biomass12 MWRetiredDecember 2020

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
60 kV
Transmission or distribution system owner
Pacific Gas & Electric Co
Balancing authority
California Independent System Operator
NERC region
WECC
Transmission lines within 25 km (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • In service · EIA-860M
  • Stated Unit GEN4 scheduled to retire, 12 MW · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source