Consumer Operations LLC
Power plant · Gas, steam turbine
Key facts
Power plant · Gas, steam turbineran 54% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 1963
- Net generation, 2025
- 224,946 MWh
- Grid
- 138 kV, 14 kV to Wisconsin Public Service Corp (MISO)
- Location
- Brown County, Wisconsin
- Operated by
- Georgia-Pacific Consumer Oper. Green Bay LLC
Output
- Gas
- Coal
- Oil
- Unspecified fuel
Details
Who’s behind it
- Owner
- Koch Industries Inc
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Gas, steam turbine source: “Natural Gas Steam Turbine”
- Age
- 63 years since 1963
- Unused energy
- 192 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
- Heat rate
- 22,762 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| EPA greenhouse gas reporting (GHGRP) |
|
| Fuel burned (MMBtu), 2025 | 5,120,296 |
| Capacity factor, 2025 | 0.539 |
| Heat rate (Btu/kWh), 2025 | 22,762.3 |
| Net generation (MWh), 2025 | 224,946 |
| Balancing authority code | MISO |
Retirement
EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.- Capacity retired
- 116.4 MW
- Generators retired
- 8
- Capacity still in service
- 47.6 MW
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| GEN1 | Conventional Steam Coal | 1.5 MW | Retired | February 2002 |
| GEN2 | Conventional Steam Coal | 3 MW | Retired | February 2002 |
| GEN3 | Conventional Steam Coal | 3 MW | Retired | February 2002 |
| GEN4 | Conventional Steam Coal | 2.5 MW | Retired | February 2002 |
| GEN8 | Conventional Steam Coal | 25 MW | Retired | December 2004 |
| GEN10 | Conventional Steam Coal | 28.2 MW | Retired | October 2014 |
| GEN5 | Conventional Steam Coal | 10 MW | Retired | October 2014 |
| GEN9 | Natural Gas Steam Turbine | 43.2 MW | Retired | September 2021 |
By technology
| Technology | Retired | Scheduled to retire |
|---|---|---|
| Conventional Steam Coal | 73.2 MW | |
| Natural Gas Steam Turbine | 43.2 MW |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Grid voltage at the plant
- 138 kV, 14 kV
- Transmission or distribution system owner
- Wisconsin Public Service Corp
- Balancing authority
- Midcontinent Independent Transmission System Operator, Inc..
- NERC region
- MRO
Transmission lines within 15 mi (10)
- Glory Rd - South Broadway 138 kV
- South Broadway - Liberty Street 138 kV
- Liberty Street - Ashland Ave 138 kV
- James St - Liberty Street 138 kV
- Liberty Street - Th Street 138 kV
- Pulliam Sw Yd - Th Street 138 kV
- James St - Pulliam Sw Yd 138 kV
- Eastman - Preble 138 kV
- Tower Dr - Van Buren St 138 kV
- Rockland Wps - Highway V 138 kV
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | Share | As of | Source |
|---|---|---|---|---|
| Georgia-Pacific Consumer Oper. Green Bay LLC | Operator | EIA-860M | ||
| KOCH INDUSTRIES INC | Owner | 100.0% | Dec 31, 2023 | EPA GHGRP |
Timeline
- Stated Unit GEN9 scheduled to retire, 43.2 MW · EIA-860M
- Stated Units GEN10, GEN5 scheduled to retire, 38.2 MW · EIA-860M
- Stated Unit GEN8 scheduled to retire, 25 MW · EIA-860M
- Stated Units GEN1, GEN2, GEN3, GEN4 scheduled to retire, 10 MW · EIA-860M
- In service · EIA-860M
Sources
5 sourcesSources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Sources
- EIA-860M
- LBNLYin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)
Around this plant
Nearby
within 15 mi| Project | Kind | Away | MW |
|---|---|---|---|
| Pulliam Postponed | Gas, combustion turbine | 3.4 mi | 170 |
| Oneida Energy Postponed | Gas, combustion turbine | 3.6 mi | 4.5 |
Sources EIA-860M