Show on map
Deepwater — Power plant · Gas, steam turbine · AES Western Power LLCTexas Petrochemicals — Gas, combined cycle · TX · 560 MW · 3.9 km awayGreens Bayou 6 — Gas, combustion turbine · TX · 445 MW · 10.9 km awayTX Houston 7080 Express Lane — Storage · TX · 1.5 MW · 11.5 km awayTX LaPort 10060 Porter Road Solar — Solar · TX · 1.6 MW · 14.9 km awayNET Power La Porte Station — Gas, combustion turbine · TX · 25.5 MW · 18.6 km awayCPV Pondera King Energy Center — Gas, combined cycle · TX · 900 MW · 20.7 km awayPamela Heights I Energy Center — Storage · TX · 101.7 MW · 23.3 km awayCallisto II Energy Center — Storage · TX · 303.2 MW · 23.3 km away
  • Combustion
  • Storage
  • In development
  • Under construction
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Gas, steam turbine

Key facts

Power plant · Gas, steam turbine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1955
Net generation, 2005
-2,616 MWh
Location
Harris County, Texas

Output

Net generation MWh by year, 2001 to 2005
Fuel burned MMBtu by year, 2001 to 2005
  • Gas

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
71 years since 1955
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110015744845
NAICS code
221112
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1008008

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
November 2005
Capacity retired
187.8 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
7Natural Gas Steam Turbine187.8 MWRetiredNovember 2005

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Transmission lines within 25 km (10)
Connection points within 25 km (4)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
AES Western Power LLC Operator EIA-860M
AES Corp Owner 100.0% 31 Dec 2023 EPA GHGRP

Timeline

  • Stated Unit 7 scheduled to retire, 187.8 MW · EIA-860M
  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · OpenStreetMap · ERCOT · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

© OpenStreetMap contributors

Sources

Every source and license · Attribution

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Texas Petrochemicals Postponed Gas, combined cycle 3.9 km 560
Greens Bayou 6 Under construction Gas, combustion turbine 10.9 km 445
TX Houston 7080 Express Lane Postponed Storage 11.5 km 1.5
TX LaPort 10060 Porter Road Solar Postponed Solar 14.9 km 1.6
NET Power La Porte Station Studied Gas, combustion turbine 18.6 km 25.5
CPV Pondera King Energy Center Postponed Gas, combined cycle 20.7 km 900
Pamela Heights I Energy Center Under construction Storage 23.3 km 101.7
Callisto II Energy Center Under construction Storage 23.3 km 303.2

Sources EIA-860M · ERCOT

Sources

Attribution