Key facts

Power plant · Gas, steam turbineran 42% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2006
Net generation, 2025
182,926 MWh
Grid
138 kV to Kingsport Power Co (TVA)
Location
Sullivan County, Tennessee

Output

Net generation MWh by year, 2001 to 2026
Fuel burned MMBtu by year, 2001 to 2026
  • Gas
  • Coal
  • Oil
  • Biomass and waste

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
20 years since 2006
Unused energy
255 GWh 2025Unused energyA lead, not a guarantee: MW × hours × (1 − capacity factor) for the latest year (EIA-923), gas, coal and oil plants only. Air-permit run-hour caps, heat rate (cost to run) and capacity-market or reliability obligations can rule it out.
Heat rate
26,842 Btu/kWh 2025
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
EPA greenhouse gas reporting (GHGRP)
EPA FRS ID
110000372329
Subparts reported
C
NAICS code
322130
Subpart PP (CO2 supply)
No
Subpart RR (geologic sequestration)
No
Subpart UU (CO2 injection)
No
Reporting year
2023
GHGRP facility ID
1005959
Fuel burned (MMBtu), 20254,910,194
Capacity factor, 20250.418
Heat rate (Btu/kWh), 202526,842.5
Net generation (MWh), 2025182,926.0
Balancing authority codeTVA

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
19 MW
Generators retired
2
Capacity still in service
50 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
NO.6Wood/Wood Waste Biomass7 MWRetiredOctober 2006
NO.7Wood/Wood Waste Biomass12 MWRetiredOctober 2006

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
138 kV
Transmission or distribution system owner
Kingsport Power Co
Balancing authority
Tennessee Valley Authority
NERC region
SERC
Transmission lines within 15 mi (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Ownership

2 companies5
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Domtar Paper Co LLC Kingsport Mill Operator EIA-860M
DOMTAR CORP Owner 100.0% Dec 31, 2023 EPA GHGRP
DOMTAR CORP Owner 100.0% Dec 31, 2023 EPA GHGRP
DOMTAR CORP Owner 100.0% Dec 31, 2023 EPA GHGRP
Domtar Corp Owner 100.0% Dec 31, 2023 EPA GHGRP

Timeline

  • Stated Units NO.6, NO.7 scheduled to retire, 19 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EPA Greenhouse Gas Reporting Program — facility register with parent-company shares (Envirofacts pub_dim_facility; FLIGHT)

Sources

Every source and license · Attribution

View at source