Show on map
Double A Digester — Power plant · Biomass · AgPower Jerome LLC
  • Bioenergy
  • Retired
  • 10 · 100 · 1,000 MW

Double A Digester

Power plant · Biomass

Key facts

Power plant · Biomassran 39% of 2019 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2011
Net generation, 2019
15,495 MWh
Location
Jerome County, Idaho
Operated by
AgPower Jerome LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2011 to 2019
Fuel burned MMBtu by year, 2011 to 2019
  • Biomass and waste

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Biomass source: “Other Waste Biomass”
Age
15 years since 2011
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeIPCO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2019
Capacity retired
4.5 MW
Generators retired
3
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Other Waste Biomass1.5 MWRetiredDecember 2019
2Other Waste Biomass1.5 MWRetiredDecember 2019
3Other Waste Biomass1.5 MWRetiredDecember 2019

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
IPCO
Transmission lines within 25 km (2)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 3 scheduled to retire, 4.5 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source