Dragon Trail — Power plant · Gas, reciprocating engine · El Paso Field Operating Co
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Dragon Trail

Power plant · Gas, reciprocating engine

Key facts

Power plant · Gas, reciprocating engine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1971
Net generation, 2001
4,292 MWh
Location
Rio Blanco County, Colorado
Operated by
El Paso Field Operating CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001
Fuel burned MMBtu by year, 2001
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, reciprocating engine source: “Natural Gas Internal Combustion Engine”
Age
55 years since 1971

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
December 2003
Capacity retired
0.4 MW
Generators retired
1
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
ICG1Natural Gas Internal Combustion Engine0.4 MWRetiredDecember 2003

Grid

Not in EIA-860Grid fieldsEIA-860 states no grid voltage or transmission owner for this plant: its annual file lists plants with a generator in the report year, so a plant that retired earlier is not in it.
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Unit ICG1 scheduled to retire, 0.4 MW · EIA-860M
  • In service · EIA-860M