Electric Light - Warrenville 138 kV — Transmission lineCYRUSONE LLC — Large load · IL · 0.7 mi awayEDGED CHICAGO LLC — Built · Large load · IL · 0.7 mi awayCYRUSONE LLC — Large load · IL · 0.8 mi awayAurora 7-SLCHI307 — Under construction · Solar · IL · 1.9 MW · 1.8 mi awayMERIDIAN PARKWAY DATA CENTER OWNER LLC — Built · Large load · IL · 1.8 mi awayCOLOVORE LLC — Built · Large load · IL · 4.6 mi awayORD-02 (West Chicago data centre) — Filed · Large load · IL · 4.6 mi away1454.07-IL 7 (Gevena data centre) — Filed · Large load · IL · 5.3 mi awayCLOP CAROL STREAM IL LLC — Built · Large load · IL · 6.3 mi awayENSONO DATA CENTER — Built · Large load · IL · 7.5 mi away360 TCS LLC — Built · Large load · IL · 8.4 mi awayGlendale Heights 10-SLCHI910 — Under construction · Solar · IL · 1.3 MW · 8.6 mi awayAddison 11-SLCHI404 — Under construction · Solar · IL · 1.6 MW · 9.3 mi awayKN216 — Under construction · Solar · IL · 4.9 MW · 11.3 mi awayInternationale Ctr 11-SLCHI321 — Under construction · Solar · IL · 1.8 MW · 11.4 mi awayCLEARBLUE TECHNOLOGIES/OAKBROOK INC — Built · Large load · IL · 11.8 mi awayNTT Data Centers — Built · Large load · IL · 13.7 mi awayAligned (Northlake data centre) — Built · Large load · IL · 14.1 mi awayNorthlake 4-SLCHI304 — Under construction · Solar · IL · 1.4 MW · 14.5 mi awayMICROSOFT CORP-CHICAGO DATA CENTER — Built · Large load · IL · 14.6 mi awayNorthlake 2-SLCHI302 — Under construction · Solar · IL · 1.6 MW · 14.6 mi awayCHICAGO ENTERPRISE LLC — Built · Large load · IL · 14.6 mi awayNALCO WATER — Built · Large load · IL · 14.6 mi awayNorthlake 5-SLCHI305 — Under construction · Solar · IL · 2.5 MW · 14.7 mi awayCyrus One V3 Point 1 — Under construction · Large load · IL · 14.7 mi awayNorthlake 3-SLCHI303 — Under construction · Solar · IL · 1.6 MW · 14.7 mi awayBensenville 2-SLCHI526 — Under construction · Solar · IL · 1.9 MW · 14.8 mi awayT5@CHICAGO III LP — Built · Large load · IL · 14.9 mi awayT5 Data Center Northlake — Filed · Large load · IL · 14.9 mi away
  • Wind & solar
  • Loads
  • In development
  • Under construction
  • Operating
  • Stage not stated
  • Size not stated
  • Other infrastructure
  • 10 · 100 · 1,000 MW

Electric Light - Warrenville 138 kV

Transmission line

Mapped route length
Mapped route length: sourceLBNL · Open license, with creditmiles
Voltage
138 kV
States crossed
US-IL

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Mapped route length (miles)
4
Substations at the ends (as the source names them)
Electric Light to Warrenville
All 2 attributes from LBNL — A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024 (OEDI submission 8742)
Attributes
AttributeValue
HIFLD line ID128745
Voltage class100-161 kV

Sources

1 source

Sources LBNL

Sources

  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.

Every source and license · Attribution

View at source

Around this line

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
CYRUSONE LLC × 2 units Unknown Large load 0.7 mi
EDGED CHICAGO LLC Built Large load 0.7 mi
Aurora 7-SLCHI307 Under construction Solar 1.8 mi 1.9
MERIDIAN PARKWAY DATA CENTER OWNER LLC Built Large load 1.8 mi
COLOVORE LLC Built Large load 4.6 mi
ORD-02 (West Chicago data centre) Filed Large load 4.6 mi
1454.07-IL 7 (Gevena data centre) Filed Large load 5.3 mi
CLOP CAROL STREAM IL LLC Built Large load 6.3 mi
ENSONO DATA CENTER Built Large load 7.5 mi
360 TCS LLC Built Large load 8.4 mi
Glendale Heights 10-SLCHI910 Under construction Solar 8.6 mi 1.3
Addison 11-SLCHI404 Under construction Solar 9.3 mi 1.6
KN216 Under construction Solar 11.3 mi 4.9
Internationale Ctr 11-SLCHI321 Under construction Solar 11.4 mi 1.8
CLEARBLUE TECHNOLOGIES/OAKBROOK INC Built Large load 11.8 mi
NTT Data Centers Built Large load 13.7 mi
Aligned (Northlake data centre) Built Large load 14.1 mi
Northlake 4-SLCHI304 Under construction Solar 14.5 mi 1.4
MICROSOFT CORP-CHICAGO DATA CENTER Built Large load 14.6 mi
Northlake 2-SLCHI302 Under construction Solar 14.6 mi 1.6
CHICAGO ENTERPRISE LLC Built Large load 14.6 mi
NALCO WATER Built Large load 14.6 mi
Northlake 5-SLCHI305 Under construction Solar 14.7 mi 2.5
Cyrus One V3 Point 1 Under construction Large load 14.7 mi
Northlake 3-SLCHI303 Under construction Solar 14.7 mi 1.6
Bensenville 2-SLCHI526 Under construction Solar 14.8 mi 1.9
T5@CHICAGO III LP Built Large load 14.9 mi
T5 Data Center Northlake Filed Large load 14.9 mi

Sources EPA ICIS-Air · EIA-860M · FAA OE/AAA · EPA ICIS-NPDES

Sources