Equinix Great Oaks Blvd. Fuel Cell
Power plant · Gas, other
Key facts
Power plant · Gas, otherran 68% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2017
- Net generation, 2025
- 26,825 MWh
- Grid
- 25 kV to Pacific Gas & Electric Co. (CISO)
- Location
- Santa Clara County, California
- Operated by
- 2016 ESA Project Company, LLCSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2025
- 26,825
MWh - Fuel burned, 2025
- 197,400
MMBtu - Capacity factor, 2025
- 68.0
% - Heat rate, 2025
- 7,359
Btu/kWh
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2025 | 26,825 | 197,400 | 68.0% | 7,359 |
| 2024 | 30,918 | 226,959 | 78.2% | 7,341 |
| 2023 | 28,182 | 203,609 | 71.5% | 7,225 |
| 2022 | 32,202 | 230,057 | 81.7% | 7,144 |
| 2021 | 32,778 | 246,762 | 83.2% | 7,528 |
| 2020 | 35,689 | 264,352 | 90.3% | 7,407 |
| 2019 | 36,982 | 256,540 | 93.8% | 6,937 |
| 2018 | 18,562 | 124,636 | 47.1% | 6,715 |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.