Show on map
Etiwanda — Power plant · Hydro · Metropolitan Water District of S CASolar Photovoltaic Project #19 — Solar · CA · 5 MW · 2.0 km awaySolar Photovoltaic Project #18 — Solar · CA · 0.5 MW · 2.4 km awaySolar Photovoltaic Project #23 — Solar · CA · 0.5 MW · 2.6 km awaySolar Photovoltaic Project #10 — Solar · CA · 0.5 MW · 3.3 km awaySolar Photovoltaic Project #04 — Solar · CA · 1.5 MW · 3.6 km awaySolar Photovoltaic Project #17 — Solar · CA · 0.5 MW · 4.0 km awaySolar Photovoltaic Project #21 — Solar · CA · 2.5 MW · 4.1 km awaySolar Photovoltaic Project #31 — Solar · CA · 1 MW · 4.1 km awaySolar Photovoltaic Project #14 — Solar · CA · 1.5 MW · 4.3 km awaySolar Photovoltaic Project #12 — Solar · CA · 0.5 MW · 7.6 km awaySolar Photovoltaic Project #08 — Solar · CA · 0.5 MW · 7.7 km awaySolar Photovoltaic Project #09 — Solar · CA · 0.5 MW · 8.0 km awaySolar Photovoltaic Project #25 — Solar · CA · 4.5 MW · 10.0 km awaySolar Photovoltaic Project #27 — Solar · CA · 1 MW · 10.1 km awaySolar Photovoltaic Project #30 — Solar · CA · 1.5 MW · 10.2 km awayRoadhouse Energy Center — Storage · CA · 300 MW · 11.5 km awayCA Bloomington 2551 S Lilac Avenue Micro — Solar + storage · CA · 3 MW · 14.6 km awaySolar Photovoltaic Project #24 — Solar · CA · 4 MW · 15.8 km awayCA Riverside 2356 Fleetwood Dr. — Solar + storage · CA · 4 MW · 16.7 km awayOES Biogas Power — Biomass · CA · 2.6 MW · 18.2 km awaySolar Photovoltaic Project #28 — Solar · CA · 0.5 MW · 23.2 km away
  • Clean firm
  • Wind & solar
  • Storage
  • Bioenergy
  • In development
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Hydro

Key facts

Power plant · Hydroran 0% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1994
Net generation, 2025
1,015 MWh
Grid
66 kV to Southern California Edison Co (CISO)
Location
San Bernardino County, California
Operated by
Metropolitan Water District of S CASourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
32 years since 1994
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
66
Transmission owner
Southern California Edison Co
Balancing authority code
CISO
Balancing authority name
California Independent System Operator
Fuel burned (MMBtu), 20253,463
Capacity factor, 20250.005
Net generation (MWh), 20251,015
Balancing authority codeCISO

Timeline

  • In service · EIA-860M

Sources

3 sources

View at source

Around this plant

Nearby

within 25 km
Projects within 25 km, nearest first.
ProjectKindAwayMW
Solar Photovoltaic Project #19 Postponed Solar 2.0 km 5
Solar Photovoltaic Project #18 Postponed Solar 2.4 km 0.5
Solar Photovoltaic Project #23 Postponed Solar 2.6 km 0.5
Solar Photovoltaic Project #10 Postponed Solar 3.3 km 0.5
Solar Photovoltaic Project #04 Postponed Solar 3.6 km 1.5
Solar Photovoltaic Project #17 Postponed Solar 4.0 km 0.5
Solar Photovoltaic Project #21 Postponed Solar 4.1 km 2.5
Solar Photovoltaic Project #31 Postponed Solar 4.1 km 1
Solar Photovoltaic Project #14 Postponed Solar 4.3 km 1.5
Solar Photovoltaic Project #12 Postponed Solar 7.6 km 0.5
Solar Photovoltaic Project #08 Postponed Solar 7.7 km 0.5
Solar Photovoltaic Project #09 Postponed Solar 8.0 km 0.5
Solar Photovoltaic Project #25 Postponed Solar 10.0 km 4.5
Solar Photovoltaic Project #27 Postponed Solar 10.1 km 1
Solar Photovoltaic Project #30 Postponed Solar 10.2 km 1.5
Roadhouse Energy Center Contracted Storage 11.5 km 300
CA Bloomington 2551 S Lilac Avenue Micro Under construction Solar + storage 14.6 km 3
Solar Photovoltaic Project #24 Postponed Solar 15.8 km 4
CA Riverside 2356 Fleetwood Dr. Under construction Solar + storage 16.7 km 4
OES Biogas Power Under construction Biomass 18.2 km 2.6
Solar Photovoltaic Project #28 Postponed Solar 23.2 km 0.5

Sources EIA-860M · CAISO

Sources

Attribution