Show on map
Farad — Power plant · Hydro · Sierra Pacific Power Co
  • Clean firm
  • Retired
  • 10 · 100 · 1,000 MW

Power plant · Hydro

Key facts

Power plant · Hydro Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1933
Net generation, 2006
-30 MWh
Grid
25 kV to Sierra Pacific Power Co (NEVP)
Location
Nevada County, California
Operated by
Sierra Pacific Power CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2006

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
93 years since 1933
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeNEVP

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
May 2006
Capacity retired
2.8 MW
Generators retired
2
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Conventional Hydroelectric1.4 MWRetiredMay 2006
2Conventional Hydroelectric1.4 MWRetiredMay 2006

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
25 kV
Transmission or distribution system owner
Sierra Pacific Power Co
Balancing authority
Nevada Power Company
NERC region
WECC
Transmission lines within 25 km (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2 scheduled to retire, 2.8 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source