Faraday — Power plant · Hydro · Portland General Electric Co
  • Clean firm
  • Operating
  • 10 · 100 · 1,000 MW

Power plant · Hydro

Key facts

Power plant · Hydroran 41% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1958
Net generation, 2025
133,129 MWh
Grid
115 kV, 57 kV to Portland General Electric Co (PGE)
Location
Clackamas County, Oregon
Operated by
Portland General Electric CoSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Hydro source: “Conventional Hydroelectric”
Age
68 years since 1958
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100001071484
Location id
L100001062249
Fuel burned (MMBtu), 2025454,236
Capacity factor, 20250.408
Net generation (MWh), 2025133,129
Balancing authority codePGE

Retirement

EIA-860M September 2026StatusSome generators have retired; the rest of the plant is still in service. As of EIA-860M for September 2026.
Capacity retired
17.4 MW
Generators retired
5
Capacity still in service
37.2 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Conventional Hydroelectric3.1 MWRetiredMay 2019
2Conventional Hydroelectric3.1 MWRetiredMay 2019
3Conventional Hydroelectric2.7 MWRetiredMay 2019
4Conventional Hydroelectric4.5 MWRetiredMay 2019
5Conventional Hydroelectric4 MWRetiredMay 2019

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
115 kV, 57 kV
Transmission or distribution system owner
Portland General Electric Co
Balancing authority
Portland General Electric Company
NERC region
WECC
Transmission lines within 25 km (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 3, 4, 5 scheduled to retire, 17.4 MW · EIA-860M
  • In service · EIA-860M

Sources

5 sources

Sources EIA-860M · GEM · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

Every source and license · Attribution

View at source