Gallatin #2
Power plant · Oil
Key facts
Power plant · Oilran 0% of 2003 Retired- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2001
- Net generation, 2003
- 62 MWh
- Grid
- SWPP
- Location
- Daviess County, Missouri
- Operated by
- City of Gallatin - (MO)
Output
- Oil
Details
Who’s behind it
- Owner
- Dean Machinery
Interested in this project?
Set an alert Book a call Join the beta
Our team gets you what you need.
Beta: private project space · data room · readiness check
- Technology
- Oil source: “Petroleum Liquids”
- Age
- 25 years since 2001
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
| Attribute | Value |
|---|---|
| Balancing authority code | SWPP |
Retirement
EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.- Retired
- September 2003
- First unit retired
- August 2003
- Capacity retired
- 3.6 MW
- Generators retired
- 2
| Generator | Technology | Nameplate | State | Date |
|---|---|---|---|---|
| 7 | Petroleum Liquids | 1.8 MW | Retired | August 2003 |
| 8 | Petroleum Liquids | 1.8 MW | Retired | September 2003 |
Grid
EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).- Balancing authority
- Southwest Power Pool
- NERC region
- MRO
Can the connection be reused?
A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.
Ownership
2 companies2| Company | Role | As of | Source |
|---|---|---|---|
| City of Gallatin - (MO) | Operator | EIA-860M | |
| Dean Machinery | Owner | Dec 31, 2025 | EIA-860 |
Timeline
- Stated Unit 8 scheduled to retire, 1.8 MW · EIA-860M
- Stated Unit 7 scheduled to retire, 1.8 MW · EIA-860M
- In service · EIA-860M
Sources
4 sourcesSources EIA-860M · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules
Sources
- EIA-860M
- EIASource: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
- EIA-860M Preliminary Monthly Electric Generator Inventory
- EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules