Gaviota Oil Plant — Power plant · Gas, combustion turbine · Freeport-McMoRan Oil & Gas
  • Combustion
  • Retired
  • 10 · 100 · 1,000 MW

Gaviota Oil Plant

Power plant · Gas, combustion turbine

Key facts

Power plant · Gas, combustion turbine Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1987
Net generation, 2020
0 MWh
Location
Santa Barbara County, California
Operated by
Freeport-McMoRan Oil & GasSourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2020
Fuel burned MMBtu by year, 2001 to 2020
  • Gas

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, combustion turbine source: “Natural Gas Fired Combustion Turbine”
Age
39 years since 1987
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeCISO

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
May 2020
Capacity retired
14 MW
Generators retired
4
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
GENANatural Gas Fired Combustion Turbine3.5 MWRetiredMay 2020
GENBNatural Gas Fired Combustion Turbine3.5 MWRetiredMay 2020
GENCNatural Gas Fired Combustion Turbine3.5 MWRetiredMay 2020
GENDNatural Gas Fired Combustion Turbine3.5 MWRetiredMay 2020

Grid

EIA-860Grid fieldsAs the plant reported them to EIA-860 (Schedule 2).
Balancing authority
CISO
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units GENA, GENB, GENC, GEND scheduled to retire, 14 MW · EIA-860M