- Wind & solar
- Operating
- 10 · 100 · 1,000 MW
Map
- Wind & solar
- Operating
GSPP Worcester Business Center, LLC: location. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
GSPP Worcester Business Center, LLC
Power plant · Solar
Key facts
Power plant · Solarran 2% of 2025 Operating- Capacity
- Capacity: sourceEIA-860M · Open licenseMW
- Commissioned
- 2025
- Net generation, 2025
- 300 MWh
- Grid
- 14 kV to Niagara Mohawk Power Corp. (ISNE)
- Location
- Worcester County, Massachusetts
- Operated by
- Green Street Power PartnersSourceEIA-860M Preliminary Monthly Electric Generator Inventory
Operations
- Net generation, 2025
- 300
MWh - Fuel burned, 2025
- 1,024
MMBtu - Capacity factor, 2025
- 2.3
% - Heat rate, 2025
- Not stated
| Year | Net generation (MWh) | Fuel burned (MMBtu) | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|---|
| 2025 | 300 | 1,024 | 2.3% | — |
How these are worked out
Net generation and fuel burned are the monthly figures EIA publishes in its bulk electricity file, from the plant's Form 923 reports; a year is the sum of its months. Capacity factor is a full year's net generation over today's nameplate capacity times the hours in that year (8,784 in a leap year), so a plant uprated or partly retired since reads against its current size; heat rate is fuel burned over net generation, for plants that burn fuel. A year with fewer than twelve months stated has no capacity factor, and a value outside the plausible range is left blank rather than shown. By month, the charts apply the same rules to each month's own hours and fuel.