Henry D King

Power plant · Gas, steam turbine

Key facts

Power plant · Gas, steam turbineran 1% of 2008 Retired
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1953
Net generation, 2008
14,425 MWh
Grid
69 kV to Fort Pierce Utilities Auth (FMPP)
Location
St Lucie County, Florida
Operated by
Fort Pierce Utilities AuthoritySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2008
Fuel burned MMBtu by year, 2001 to 2008
  • Gas
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Gas, steam turbine source: “Natural Gas Steam Turbine”
Age
73 years since 1953
1 attribute from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Balancing authority codeFMPP

Retirement

EIA-860M September 2026StatusEvery generator EIA lists at this plant has retired. As of EIA-860M for September 2026.
Retired
May 2008
Capacity retired
141.8 MW
Generators retired
7
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
5Natural Gas Fired Combined Cycle8.3 MWRetiredMay 2008
6Natural Gas Steam Turbine16.5 MWRetiredMay 2008
7Natural Gas Steam Turbine33 MWRetiredMay 2008
8Natural Gas Steam Turbine56.1 MWRetiredMay 2008
9Natural Gas Fired Combined Cycle22.5 MWRetiredMay 2008
D1Petroleum Liquids2.7 MWRetiredMay 2008
D2Petroleum Liquids2.7 MWRetiredMay 2008
By technology
Nameplate capacity retired or scheduled to retire, by technology
TechnologyRetiredScheduled to retire
Natural Gas Steam Turbine105.6 MW
Natural Gas Fired Combined Cycle30.8 MW
Petroleum Liquids5.4 MW

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
69 kV
Transmission or distribution system owner
Fort Pierce Utilities Auth
Balancing authority
Florida Municipal Power Pool
NERC region
SERC
Transmission lines within 15 mi (10)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 5, 6, 7, 8, 9, D1, D2 scheduled to retire, 141.8 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution

View at source

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Spanish Moss Under construction Solar 14.5 mi 74.5

Sources EIA-860M

Sources