Show on map
Hilton Head — Power plant · Oil · South Carolina Public Service Authority
  • Combustion
  • Operating
  • 10 · 100 · 1,000 MW

Hilton Head

Power plant · Oil

Key facts

Power plant · Oilran 0% of 2025 Retiring
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
1973
Net generation, 2025
79 MWh
Grid
115 kV to South Carolina Public Service Authority (SC)
Location
Beaufort County, South Carolina
Operated by
South Carolina Public Service AuthoritySourceEIA-860M Preliminary Monthly Electric Generator Inventory

Output

Net generation MWh by year, 2001 to 2025
Fuel burned MMBtu by year, 2001 to 2025
  • Oil

Operations detail

Details

Who’s behind it

No companies named in filings yet.

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Oil source: “Petroleum Liquids”
Age
53 years since 1973
All 4 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Fuel burned (MMBtu), 202517,140
Capacity factor, 20250.000
Net generation (MWh), 202579
Balancing authority codeSC
Data notes (1)
  • Heat rate (Btu/kWh), 2025 not shown: computed 216962.0 outside 5000-30000 Btu/kWh

Retirement

EIA-860M September 2026StatusAt least half of the plant's in-service nameplate capacity is scheduled to retire, on dates its owner has reported to EIA. As of EIA-860M for September 2026.
Next scheduled retirement
December 2033
Capacity scheduled to retire
117.9 MW
Generators scheduled to retire
3
Share of in-service capacity scheduled
100%
Capacity still in service
117.9 MW
Generators that retired or are scheduled to retire
GeneratorTechnologyNameplateStateDate
1Petroleum Liquids26.6 MWScheduled to retireDecember 2033
2Petroleum Liquids26.6 MWScheduled to retireDecember 2033
3Petroleum Liquids64.7 MWScheduled to retireDecember 2033

Grid

EIA-860 2025Grid fieldsAs the plant reported them to EIA-860 for 2025 (Schedule 2).
Grid voltage at the plant
115 kV
Transmission or distribution system owner
South Carolina Public Service Authority
Balancing authority
South Carolina Public Service Authority
NERC region
SERC
Transmission lines within 15 mi (1)
Can the connection be reused?

A plant that retires usually leaves its substation, transmission connection and interconnection agreement behind, and those may be reusable by a new project at the same site. FERC Order No. 845 lets an interconnection customer use surplus interconnection service at an existing site, and some transmission providers' tariffs let a replacement resource take over a retiring unit's interconnection service, usually within a set time after the retirement. Whether any such right still exists here, who holds it and on what terms depends on the owner, the transmission provider and timing; this page does not establish any of that.

Timeline

  • Stated Units 1, 2, 3 scheduled to retire, 117.9 MW · EIA-860M
  • In service · EIA-860M

Sources

4 sources

Sources EIA-860M · LBNL · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • LBNLOpen license, with credit · retrieved Nov 13, 2026Yin, Nait Belaid & Heleno (2026), Lawrence Berkeley National Laboratory, OEDI, CC BY 4.0: A Harmonized Geospatial Dataset of U.S. Transmission Lines: Linking FERC Form 1 and HIFLD, 1994-2024. Modified by Inframation: HIFLD-side fields only, names re-cased, coordinates rounded.
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory

Every source and license · Attribution