Show on map
Horn Rapids Solar, Storage and Training — Power plant · Solar · Energy Northwest
  • Wind & solar
  • Operating
  • 10 · 100 · 1,000 MW

Horn Rapids Solar, Storage and Training

Power plant · Solar

Key facts

Power plant · Solarran 13% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2020
Net generation, 2025
4,621 MWh
Grid
72 kV to City of Richland - (WA) (BPAT)
Location
Benton County, Washington
Operated by
Energy Northwest

Output

Net generation MWh by year, 2020 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Solar source: “Solar Photovoltaic”
Age
6 years since 2020
All 6 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Gem
Unit ids
G100000816102
Location id
L100000813400
Eia plant ids
64198
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
72
Transmission owner
City of Richland - (WA)
Balancing authority code
BPAT
Balancing authority name
Bonneville Power Administration
Fuel burned (MMBtu), 202516,717
Capacity factor, 20250.126
Net generation (MWh), 20254,621
Balancing authority codeBPAT

Solar array

Array area (acres)
15
AC capacity (MW)
3.2
DC capacity (MW)
4
Mounting
Fixed tilt
Site type
Greenfield
Began operating
2020

Source USPVDB

Source

  • USPVDBOpen license · retrieved Oct 25, 2026Map services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb

Attribution

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Energy Northwest Operator EIA-860M
Tucci Energy Services Owner 76.2% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Sources

6 sources

Sources EIA-860M · GEM · USPVDB · EIA · EIA-860M Preliminary Monthly Electric Generator Inventory · EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • GEMOpen license, with credit · retrieved Oct 26, 2026Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
  • USPVDBOpen license · retrieved Oct 25, 2026Map services and data are available from Large-Scale Solar Photovoltaic Database, provided by the U.S. Geological Survey and Lawrence Berkeley National Laboratory via https://energy.usgs.gov/uspvdb
  • EIAOpen license · retrieved Nov 1, 2026Source: U.S. Energy Information Administration, Electricity bulk data (Form EIA-923 monthly plant series)
  • EIA-860M Preliminary Monthly Electric Generator Inventory
  • EIA-860 Annual Electric Generator Report — Schedule 4 Owner (ownership shares per generator), plus Plant/Generator schedules

Every source and license · Attribution